Pass Milestone activity
An activity that, when used together with the Wait For Milestone activity, lets a process wait for an event that is not in the process, and then continue once the event is complete. For example, if an activity can not start until an approval occurs in a subprocess, you can use this activity to control the process based on that event..
Configure the Pass Milestone activity
To configure the Pass Milestone activity, do the procedure in this topic.
Examples
- (Example) Configure a Pass Milestone Activity in the Human Resources Leave Verification Subprocess
- Examples - Step-by-step use case examples, information about what types of examples are provided in the AgilePoint NX Product Documentation, and other resources where you can find more examples.
Good to Know
- In most text fields, you can use process data variables as an alternative to literal data values.
- You can configure whether this activity waits for other activities before it runs.
For more information, refer to How Do I Configure an Activity to Wait for Other Incoming Activities?
How to Start
- On the Application Explorer screen, do one of these:
- Do one of these:
- Add an activity:
- In the Process Builder, in the Activity Library, open the Utilities tab.
- On the Utilities tab, drag the Pass Milestone activity onto your process.
- Change an activity:
- In your process, double-click your activity.
- Add an activity:
Procedure
- Complete the fields on the
General Configuration screen.
For more information, refer to Configure General Options for a System Activity.
- (Optional) Click Advanced >
E-mail Notifications .
For more information, refer to Configure E-mail Notifications for Any Activity.
General Configuration
Specifies the basic settings for the Pass Milestone activity.
Fields
Field Name | Definition |
---|---|
Display Name |
|
Description |
|