How Do I Configure an And Activity?
To configure an And activity, do the procedure in this topic.
How to Start
- On the App Explorer screen, do one of these:
- Do one of these:
- Complete the fields on the General Configuration screen.
Procedure
- On your process, click your And activity.
- In Process Builder, click Properties > 
          Model Properties.
           
- On the Properties screen, in the Advanced section, set the 
            Dynamic property as necessary.
          
            Field Name Definition Dynamic - Function:
- Specifies which direct predecessor activities to wait for before starting the activity at runtime.
- Accepted Values:
- 
                - True - Specifies that the activity starts only after all of the activity's direct predecessors are 
                    Completed, along with all preceding activities 
                    in the process branch. This setting ignores activities that are skipped or bypassed 
                    because of the process logic or manual action in the 
                    Manage Center.
                    This setting is the logically the same as setting the Wait All Incoming property for a system activity to True (Dynamic). 
- False - Specifies that the activity starts only after all of the activity's direct predecessors are Completed.All other activities process are ignored.
                    
                    If any of activities in the process branch is delayed or does not start, this activity will not start, the process instance can be delayed indefinitely at this activity. This setting is the logically the same as setting the Wait All Incoming property for a system activity to True (Static). 
 
- True - Specifies that the activity starts only after all of the activity's direct predecessors are 
                    Completed, along with all preceding activities 
                    in the process branch. This setting ignores activities that are skipped or bypassed 
                    because of the process logic or manual action in the 
                    Manage Center.
                    
- Default Value:
- True
- Accepts Process Data Variables:
- No
 
Example: Dynamic = True

Configuration:
On the And activity, Dynamic is set to True. This is the default setting
Result:
The Salesforce Update Entity activity starts only if the SharePoint Retrieve List Item, Databse Query Record, and Timer activies are all complete.
Example: Dynamic = False

Configuration:
On the And activity, Dynamic is set to False
Result:
If both the SharePoint Retrieve List Item activity and the Database Query Record activity complete, the Salesforce Update Entity activity starts, regardless of the status of any other activities in the process.
 
         
                     
                    