Mark Task As Complete activity

An activity that marks a task as completed in Asana.


Mark Task As Complete activity

Configure the Mark Task As Complete activity

Prerequisites

Good to Know

How to Start

  1. Open Process Builder.

    For information about how to open this screen, refer to Process Builder.


    Open Process Builder
  2. In Process Builder, in the Activity Library, open the Asana tab.

    Open Asana tab
  3. On the Asana tab, drag the Mark Task As Complete activity onto your process.

    Drag Mark Task As Complete activity

General Configuration

Specifies the basic settings for the Mark Task As Complete activity.

Figure: General Configuration screen

General Configuration screen

Good to Know

  • Documentation for this screen is provided for completeness. The fields are mostly self-explanatory.

Fields

Field NameDefinition

Display Name

Description:
Specifies the activity name that shows in your process.
Allowed Values:
One line of text (a string).

Accepted:

  • Letters
  • Numbers
  • Spaces
Default Value:
None
Accepts Variables:
No
Example:
This is a common configuration field that is used in many examples. Refer to:
  • Examples - Step-by-step use case examples, information about what types of examples are provided in the AgilePoint NX Product Documentation, and other resources where you can find more examples.

Description

Description:
Specifies an optional text description for your activity.
Allowed Values:
More than one line of text.
Default Value:
None
Accepts Variables:
No

Mark Task As Complete Configuration

Specifies the information about a task to mark as completed in Asana.

Figure: Mark Task As Complete Configuration screen

Mark Task As Complete Configuration screen

Fields

Field NameDefinition

Asana

Description:
Specifies the access token that connects to your Asana service.
Allowed Values:
A list of access tokens configured for your environment.
Default Value:
None

Create Add Token icon

Opens this Screen:
Access Token for Asana
Function of this Screen:
Configure an access token to connect to Asana.

Task ID

Description:
Specifies the ID of the Asana task to mark as completed.
Allowed Values:
An integer that represents an Asana task ID.

The task ID comes from Asana.

Default Value:
None
Accepts Variables:
Yes
Limitations:

Some information about third-party integrations is outside the scope of the AgilePoint NX Product Documentation. It is the responsibility of the vendors who create and maintain these technologies to provide this information. This includes specific business use cases and examples; explanations for third-party concepts; details about the data models and input and output data formats for third-party technologies; and various types of IDs, URL patterns, connection string formats, or other technical information that is specific to the third-party technologies. For more information, refer to Where Can I Find Information and Examples for Third-Party Integrations?